The ISO/IEC 27001 management review is the meeting at which top management checks the ISMS at planned intervals: is it still suitable, adequate and effective? Clause 9.3 lists the inputs, and the outcome is decisions on improvements and changes. Taking note is not enough.

Internal audit program of the demo company with topic coverage, cycle, objectives, criteria and methods
Inhoud
  1. What clause 9.3 requires
  2. The inputs at a glance
  3. The procedure in five steps
  4. Template for the minutes
  5. The most common mistakes
  6. Example from industry
  7. Checklist
  8. The management review in Complass
  9. Frequently asked questions
  10. Read more

Stand van:

This guide shows the inputs, the procedure in five steps and a template for the minutes. The standard is paraphrased in our own words, and the examples are invented.

What clause 9.3 requires

  • Planned intervals. The standard sets no cycle. At least one meeting a year is common.
  • Top management. It carries out the review itself. The CISO may prepare it.
  • Defined inputs. Clause 9.3.2 lists the topics that feed into the review.
  • Decisions. The results include decisions on improvements and on changes needed to the ISMS.
  • Evidence. The results must be available as documented information.

Before a certification audit, certification bodies usually expect a completed management review. The standard itself sets no time for it.

The inputs at a glance

Structure the report and minutes by these inputs, and the auditor finds everything at once.

InputQuestion for managementTypical source
Earlier reviewsWhat became of the last decisions?Action list
Internal and external issuesWhat has changed around us?Context document
Interested partiesWhat do customers, authorities and others expect today?Customer requests, new laws
Nonconformities and corrective actionsWhich findings are open?Findings register
Measurement resultsHow are the key figures developing?Key figures under 9.1
Audit resultsWhat did internal and external audits show?Audit reports
ObjectivesHow far are the security objectives met?Objectives plan under 6.2
FeedbackWhat do stakeholders report back?Customers, staff, service providers
RisksWhat is the risk situation, how far is the treatment plan?Risk register
ImprovementWhere can the ISMS get better?Suggestions, lessons from incidents

The procedure in five steps

  1. Set the date. Plan it after the internal audit so that the results feed in.
  2. Prepare the report. The CISO summarizes the inputs on a few pages and names the open decisions.
  3. Review. Management goes through the inputs and judges: is the ISMS suitable, adequate and effective?
  4. Decide. Record every decision with an owner and a date.
  5. Follow up. The decisions go into the action plan and are the first input to the next review.
Action plan of the demo company with owners, due dates and status
Action plan: every decision becomes a task with an owner and a date.

Template for the minutes

Copy the table into your own template. The entries on the right are invented examples.

SectionExample
Date and participants12 March, managing directors, CISO, head of IT, head of production
Status of earlier decisions5 of 6 done, segmentation of hall 2 postponed
Changes around usMajor new customer asks for evidence, new plant planned
ISMS performanceOpen findings 7, training rate 92%
AuditsInternal audit: 2 nonconformities, 5 recommendations
Objectives3 of 4 objectives met
FeedbackTwo customer questionnaires, no complaint
Risks and treatmentRemote maintenance still high, treatment plan 70% done
ImprovementsExtend the incident exercise to the night shift
DecisionsBudget for remote maintenance released, owner: head of IT, date: 30 June
Overall judgmentISMS suitable and adequate, improve effectiveness for remote maintenance

The most common mistakes

  • Only taking note: The minutes contain not a single decision.
  • Without management: The CISO reviews alone and management only signs.
  • No follow-up: Decisions from last year no longer appear anywhere.
  • Wrong order: The meeting comes before the internal audit, so its results are missing.

Example from industry

The example is invented. An automotive supplier puts the review on the agenda of the management meeting. Two hours are enough because the CISO circulates the report a week before.

  • Insight: Customers ask more often about OT security, but production is only partly in scope.
  • Decision: The scope grows in the next cycle, and one position is added.
  • Evidence: Minutes with owners and dates, tasks in the action plan.

Checklist

  • The date falls after the internal audit.
  • Top management takes part.
  • All inputs under clause 9.3.2 are covered.
  • The overall judgment on suitability, adequacy and effectiveness is in the minutes.
  • Decisions on improvements and changes are made.
  • Every decision has an owner and a date.
  • The minutes exist as documented information.
  • The status feeds into the next review.

The management review in Complass

No more collecting figures before the meeting. Complass builds the report from what is already in your ISMS:

  • Management report: A PDF structured like clause 9.3, with key figures and trends, also as PowerPoint.
  • Inputs: Complass shows which inputs the report covers. You state changes around you with yes or no.
  • Results: Every result becomes a task in the action plan, with an owner and a deadline.
  • Findings: You record nonconformities directly in the findings register.
  • Confirmation: The participating members of management confirm in person. The status is then filed as evidence.
  • Template: The ISO 27001 module contains a document for the minutes with guidance.

Frequently asked questions

How often do we have to carry out the management review?

The standard requires planned intervals and sets no cycle. At least once a year is common, and more often after major changes.

May the CISO carry out the review alone?

No. Clause 9.3 addresses top management. The CISO prepares and reports.

Does management have to sign the minutes?

The standard does not require a signature. It has proven useful as evidence of participation and decisions.

Can we combine it with the ISO 9001 review?

Yes. Keep the ISMS part clearly visible so that all inputs of clause 9.3.2 can be seen.

Does the management review replace oversight under § 38 BSIG?

No, but it supports it. § 38(1) BSIG (German BSI Act) requires oversight of the measures under § 30 BSIG. In our view one review a year is hardly enough for that. Our guide on § 38 BSIG shows a quarterly rhythm.

In a demo we show you how ISMS data becomes a report and how decisions become tasks.

Request a demo Try it for 14 days

Read more

Not legal advice. This guide gives a general overview and does not replace an assessment of the individual case. The wording of your licensed edition of the standard is authoritative. As of November 2026.